July 16 2019

Project Field Work Start

Field work such as topographic and legal surveys, geotechnical investigations, underground utility locates and other work necessary for the design of the works is expected to start late-July
September 30 2019

Field Work Completion

Field work such as topographic and legal surveys, geotechnical investigations, underground utility locates and other work necessary for the design of the works is expected to start late-July and completed mid-September 2019.